Project Time Line
Currently, it is expected that the Financial System Upgrade will be complete and available for campus use on Monday, March 26, 2012.
An alternate date of Monday, April 16, 2012 has been reserved if needed.
System Testing: August 2011 – October 2011
CO Acceptance Testing: September 2011 – December 2011
Campus Acceptance Testing: November 2011 – December 2011
Performance Testing: September 2011 – February 2012
Campus Training & Workflow Conversion: January 2012 – March 2012
Financial System Down (for Upgrade): March 22nd at 2 PM
Go-Live: March 26 by 2 PM
Financial 9.1 Upgrade Project Timeline